how to estimate plastering quantity if the given object is in circular. 12 mm thick both side 1:3
example= i have 8.15 m2 how to estimate quantity
Answer Posted / sreejith
I will give the basic for calculating the plastering quantity for 100 m2.You can use the same way based on your required mortar volume
Let Area to be plastered=100 m^2
& Thickness of plaster= 12mm=(12/1000)m= 0.012m
Volume of mortar required= 100 x 0.012= 1.20 m^3
Add 20% extra mortar for filling joint,depressions and
wastage.
Volume of the mortar= [0.20 X 1.20]+ 1.20=1.44 m^3
[Wet Volume]
Increase further by One-third of the volume to get Dry
volume
Quantity becomes= [(1/3) X 1.44]+ 1.44=1.92 m^3
Summation of proportion=1+5=6
For 12mm plastering in 1:5 cement:sand mortar mix,
1)Cement required= 1.92/6= 0.32 cu. m
No. of bags of cement= 0.320/0.0347=9.22 bags
>>9 bags(say)
Kgs of cement required=9 x 50= 450 kg (approx)
2)Sand required= [1.92 x (5/6)]= 1.60 cu. m
[Weight of 1 bag of cement= 50 kg
Cement should be always measured by weight to avoid
variation.
One 50 kg bag of cement weighs 1440 kg/cu. m
Volume of 1 bag of cement= 50/1440=0.0347 cu. m ]
Therefore to convert Cu. m into No of bags of 50 kg
cement,just divide the volume of cement by 0.0347
| Is This Answer Correct ? | 5 Yes | 0 No |
Post New Answer View All Answers
115mm thickness brick work how to required mortar
What is the sugested procedure of water purification for public supply?
what are the changes in concrete pour height as per IS 456, 2009?
sir when can we expect the AEE results and when will be the interviews sheduled please guide us in this regard thanking you
How to measure the requirement of cement n sand for 12mm and 20mm plastering thanks in advance
why steel tanks are provided (a) for water pressure (b) for wind pressure (c) for earthquake pressure
Can we use Polystyrene as a Bitumen modifier !! if so is it a good MS research topic ? and what type of laboratory tests will be conducted during Research work ??
Hi I had missed my mark list (first year-apr2003)how i search in my old mark details in internet and which web site? pl inform me in full details..
How to Know that veriation acceptable in CPWD Work Of 1:6 Cement Mortor Received Lab test report.
what is escalation?how it is done?
load combinations how many types for staad design purpose?
How do you calculate the unit weight of concrete?
can any one explain bar bending schedule of bems and columns and slabs ??
In few lines, please be elaborative on extras and talents that make you a potential candidate for the post:
Slump Values for works?