Please tell me the difference between nominal and clear
cover. Thanks.
Answer Posted / suchith kumar
effective cover=the distance from centre of iron rod to the bottom of fibre.
clear cover=the distance from bottom of fibre to bottom of iron rod.
| Is This Answer Correct ? | 20 Yes | 6 No |
Post New Answer View All Answers
detailed calculation of the amount of cement used?
A doubly reinforced concrete beam is 25 cm wide and 50cm deep to the centre of tension reinforcement. The centre of compression is steel is 5cm from the compression edge. The areas of the compression and the tension steel are 10.16cm2 and 12.56 cm2 if m=18 and the bending moment at the section is 7,000,000 N-cm. Calculate the stress in concrete and steel.
Define What is unit weight of normal concrete?
how to estimate man power for estimating the time required for completion of a project in terms of carpenters,barbenders,masons for block work ,masons for plasteing ,unskilled labour, painters, tiles masons,plumbers and electricians for medium and high rise constructions and independent villa projects.
How much is the cover for slab?
why do we not deduct volume of steel to find actual volume of concrete in practical???
What is meant by a context menu in a cad software?
what mean By core Billing
1. What is coefficient use for calculation of shuttering. 2. What is coefficient use for calculation of reinforcement in one cum of concrete.
I want to know the relevant IS codes of practice which deals with different testings of cement-sand mortar (nominal mix)that is being normally used for brick work or plaster work in the construction work.
column at edge of a framed structure is uniaxial or biaxial. and is an interior column is biaxial
660 square fit two story house make totally how much cement, sant, brick,aggregate, steel totally how much need
what is the Asfalt test?in road constraction..?
if dia of slab beam bar is38mm what its clear cover any method of provide clear cover
Labor requirement for each item needed? Lean Concrete 103.550m3 Concrete for Foundation and Structure 1753.000m3 Expansion joint 288.000m Contraction joint 127.000m Dowel bar 450.000m