Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

How to connect field devices to PLC and DCS using a FIELD
BUS, DP,MOD BUS(please tell me any extra interfce or
adopters need in this case if we use remote i/o s)

Answer Posted / rajendra singh

first of all I want to tell you connection from field to DCS:

Example: C.V. to Tx. to controller via Ethernet cable to DCS.

Is This Answer Correct ?    2 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What are the interlocks we have to check during the start up of LP/HP compressor?

1931


Why is it necessary to use compensation leg to measure the liquid level in a closed or pressurized tank?

2392


what is the importance of CV in the control valves? how it is calculated?

2383


Define cryogenic?

1082


HOW TO SOLVE PROBLEM WITH ENRAF LEVEL TRANSMITTER 854 ATG THAT PASSWARD DO NOT Exist INTO TRANSMITTER TO ADJUST LEVEL WITH PORTABLE PET 847, WRITTEN WRONG PASSWORD , I AM SURE THAT DEFAULT PASSWARD (W2=ENRAF2) IS THIS TRANSMITTER NEED TO REPLACE SOFTWARE AND HOW?

3453


what is metal of piston ring

1860


what step is taken for ESD ( emergency shut down) in DCS REPLY to hashimka20009@gmail.com

2261


Hi,can anyone help me out with PhD programs related to Instrumentation field?I have a degree in electronic Instrumentation?

1867


Why humidity limit is 30 to 55 % for raw material storage?

4210


What is the difference between ff transmitter and non ff transmitter

2390


If a control valve is hunting means means if we are giving 50% to the cv, the cv will open at 51% then slowly slwoly it will reaches 49% , so what to do for solve this problem. The cv is double acting and mounted for anti surge operation, it having 4 nos. volume booster, one sov, one positioner, etc..?

2021


Calibration of controller (pneumatic)

1907


what should he know if he is an assitent engineer instrumentation in cement industries of experience of 10 - 15 year.

2041


field bus transmitter calibration procedure tell me

1771


A PLC is programmed to drive three motors A, B and C as follows : After running motor A for an hour, motor B should get ON and motor A should get OFF. And after running motor B for an hour, motor C should get ON and motor B should get OFF. And after running motor C for an hour, motor A should get ON and motor C should get OFF. (That is, a cyclic repetition with time period one hour) Now, the second condition is: If any motor gone faulty and is tripped, the consecutive motor should get ON and the faulty (tripped) motor should be eliminated from cyclic repetition. The remaining two motors should bear the cyclic repetition of one hour each. (For healthy motor take logic as high and for tripped motor take logic as low) Now, the third condition is: When motor A load(Amps) exceeds 60% of its rated load, motor B should get ON in parallel to motor A. And when both motors A & B are running in parallel, and if their load exceeds 60% of their rated load, motor C should also start in parallel to A & B. [Here the cyclic repetition is eliminated, until their loads become normal(40%)] [Take logic high(1) for load at 60% and logic low(0) for load at 40%] Now draw a flow chart or a ladder diagram to fulfill the above condition.

2112