1. how Product Cost Collector Works?
2. What are the master data for MRP?
3. In a production order without making goods issue, i should
not be able to do goods receipt. How do we do it?
4. i have one particular part 'A'. it is available in two
storage location X & Y. when i run MRP, I don't want MRP to
consider stock that are available in storage location Y. what
should be done.
5. for in-house production, planned order are generated & for
external procurement purchase requisition. i want, system will
go in external procurement to a particular vendor. what is the
setting?
6. what are the problems you faced in MRP?
Answer Posted / hayat khan
1. It captures all Dr and Cr related to the GR and GI for the respective material.
2. MRP controller, MRP controller for missing parts, PPC calender, Shedule margin key, MRP area, MRP type, Procurement tYPE, SPECIAL procuremement type etc
3. In confirmation parameters set indicator "termination for incorrect goods movement"
4. set MRP indicator 2 in MRP4 view for storage location Y
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
In project the customization is comes under which phase?
What is a ‘work center’ in pp?
what are the constraints of Variant configuration?
What is purpose of schedule margin key?
Scheduling times can be defined in the material master record by?
What is alternate item group?
Tell some standard order types and what configure done for current project
What are the steps of production execution process?
What does the use of ms70 followed by mcec get you?
Explain what happens to planned after it has been converted into production order?
Explain Availability check.
Which tool you are using
suppose we have sales order-40, PIR-25,warehouse stock-40, so when we run mrp,what quantity the system displays with MTO & MTS. How?
What are the ‘bom categories’ supported by sap?
Can we have more than 6 standard values in standard value key?