We are using 4 MVA transformer and we provided 2 separate earthing pit for Body and 2 separate earthing pit for neutral, can we connect separate body earthing pit to other earthing pit (Equipment earthing)?
Answer Posted / riaz abbasi
No, we can not connect equipment earthing with body earthing because in case of earth fault , current will also run in the body via equipment earthing system and will damage other equipments which are installed over the Transformer.
Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
What are the main significances of root locus?
How to calculate the Efficiency of Chiller
internally connection of photvoltic module
H.t motor 6600 volt to same motor lt supply 440volt supply applyed to h.t motor to effect....
Can any one give an explanation about rating factors of cable? if we are laying the cable on the air with an temp 15 degree then rating factors will be 1.15 and if we are laying the cable on the air an temp 60 degree then rating factor will be 0.76 please describe it and what is the difference between rating factor and derating factor?
What are the different types of hydro schemes?
How relay works, reverse relay, master relay, os relay, earth fault relay and what is its setting point
why ten delta testing is carried out on power transformer
what is power factor ? how we can calculate the low power factor and amount of capacitor for improve that low factor ?
What is the rating factor for copper cable ( Specific value according to the type of laying ) & the voltage drop?
Explain using drawings what is reverse PID action w.r.t PID controllers.
Please provided formula for calculate the cable size from step up transformer to M.V panel, run overhead aluminum cables, total load is 5mega watt, total length 900 feet.
If anyone would like to know or practice for FEWA papers contact me on mohamedrashad2@hotmail.com Just completed the supervisor exam in April 2021
Why the symbol of register is "zig zag"
What is the de rating factor of cable? What is the importance of the de rating factor in cable selection?