What is the step by step process in MRP
Answer Posted / puneet
Step By Step Procedure In Sap MRP Run
Firstly You Have to Check MRP Activate or Not For that Plant/Organisation.
2nd One You have to check Particulur MRP Area.
Step to Run MRP.
Step1.Create Material Master
Select The Views like General Data,Purchasing,MRP1,MRP2 and Accounting.
When we insert General data or purchasing Data after coming to MRP1 View we have to fill this field mandatory (Lot Size,Reorder Point,Safety Stock)
In The MRP2 View we have to filled planned Delivery Time.
after done accounting view.
Save.
when we run MRP
Single item Single Leve t-code is MD03
Single item Multiple Level MRP Run T-Code Is MD02
when we Run MRP On SIngle item Single level.
by behalf of MRP Run with re-order point .
when the material fall down to re-order point.
Automatically Re-order Point Triggerd in MRP.
PR Generated Automatically. you can Create PR-PO By Double click of That PR.
After That You can Check or Display MRP on Material By t-code MD21
Is This Answer Correct ? | 2 Yes | 1 No |
Post New Answer View All Answers
Explain the types of third party stocks in sap mm
Explain the 'accounting' side of gr?
How you can link a document to a vendor master record?
What is mysap erp?
How is the vendor created?
Explain how consignment stocks are created?
Where do we define payment terms in po?
What is purchase requisition as related to sap? Mention the document types that are used in purchase requisition?
What do you mean by forecast-based planning?
Suppose you purchase new air filters and return the old damaged filters. This is a case of purchase and return simultaneously. How will you map such business scenario in sap mm?
Which facility of sap will you use if you want to maintain different moving price of a material based on its origin? For ex: there is a motor if purchased from a domestic vendor or if purchased from a overseas vendor. How will you maintain different moving average price for both cases.
What are the variousfeatures of consignment stocks?
What is a material master file?
What is mrp (material requirement planning) and what is the transaction code to access mrp list?
How does material price copy into a purchase request? What is the sequence of priority for copy price in pr?