how many kg sand is requried for plastring in 100 sqft?
Answer Posted / ravi naik (ravinaik013@gmail.c
If the ratio is 1:3
First find the volume of mortar.
If we take thickness as 12mm = 0.012mt
For 100 Sq. Feet = 9.29 m2
Mortar volume = 9.29*0.012
= 0.1115 m3
Increase Volume of mortar by 60% ( this volume includes filling joints,depression,voids and dry volume of material)
So increased volume = 0.1115*1.6
= 0.178m3
Cement in bags = (0.178*1/4)/0.0347
= 1.28 bags
Sand in kg = (0.178*3/4)*1840
= 0.1335*1840
= 245.64 kg
(Bulk density of river sand =1840kg/m3)
Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
how to do cementicious paint for rcc walls of cw pump house
What is the software used in civil engineering?
Explain what is Hybrid Foundation?
How much does it cost for a R.C.C cover slab of size (450mmX 600mmx 100mm) double rf net given in feets using hand mix concrete?
how to decide the mortar ratio 1:4,1:6 in masonry? same in plaster 1:3 and 1:4? which code or any document reference taken to define proportion?
a) we have 30nos., 300mm dia, 4m length double under reamed piles.calculate excavation quantity.b) tell concrete qty. also.
how much brick, cement, and sand required in 1mtr X 0.23mtr X 1mtr brickwork(1:4), 230mm thick wall and 10mm thick mortar , brick size 230mm X 70mm X 110mm
What glue is least sticky?
What is the use of water table & Kreb stone for drain
What is the procedure and technnology behind jointing of prestessed block in Delhi metro rail project.
TO CONSTRUCT A 1800 SQFT CAPACITY UNDERGROUND WATER TANK HOW MUCH CUFT CONCRETE IS REQUIRED AND HOW MUCH REINFORCEMENT IS REQUIRED. FOR COSTING
Why do you want to work here
What is the mix propotion of M10,M15,M20,M25,M30,M40,M50.M60 cement content,aggrigate,sand and water ratio.
What is the quantity of cement in mix m20 concrete?
brickwork labour rate per cum ?