Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

whats are the max value of providing of super-elevation in
road way in various condition?

Answer Posted / surendar,ap,velammal engg

7% for plain and rolling terrain
10% for hilly roads
4% for urban road stretches with frequent intersections

Is This Answer Correct ?    2 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Why do we not deduct steel volume to find actual volume of concrete in practical as we have studied that,,, actual volume of concrete = volume of column- volume of steel pls explain with reference of IS code?????

2125


what is meant by sustainable developement as far construction field is considered. Give suitable examples to explain the same

2292


List out some of the software program that can be useful for architect?

1166


How many are the types of joints?

1236


How to measure the requirement of cement n sand for 12mm and 20mm plastering thanks in advance

3076


1m square 20mm plastering how much of water need curing work

1948


I would like to get the formula How can i calculate the productivity of a mason in terms of brick laying and plaster. i have 6000 Sqmt of interlock laying work i want to calculate - how many masons required to do the job - in how many days can it be done - what will be the production rate in 8 hours shift/ per mason if i can get some excell sheet , it will really help me in my calculations

1539


What is a kip?

1265


Explain the benefits of using standard terminology in the measurement process?(Tendering and estimation)

5103


What are the ingredients of pre-stressed concrete?

1302


What is fineness modulus ? and its sieve # ?

1469


door and window wood work calculations and different methods

2213


How do we calculate the power of centrifugal pump?

1214


how to calclate the SHUTTERING TAKEN CONCRETE LOAD? WHAT IS THE LOAD BEARING CAPACITY IN STEEL SHUTTERING PLATE? WHAT IS THE CONCRETE LOAD IN (MASS) IN THE SHUTTERING PLATE. PLATE SIZE IS 120CM* 90CM CONCRETE WALL LENGTH IS 10M ,WIDE IS 60CM, HEIGHT IS 1.2M PLS TO SENT THE CALCULATION.

11120


What is the quantity of cement in mix m20 concrete?

1230