HOW we can calculate the quantity of sand and cement for 1:4
plastering with a thickness of 12 mm..total area need to be
plaster is 985 sqm
Answer Posted / eakub.molla
Total area=985m2
thickness of plaster=12mm=.012m
wet volume of plaster morter=985*.012=11.82m3
dry volume of morter=11.82*1.5=17.73m3
volume of cement=17.73/5=3.546m3
volume of sand=14.184m3
cement bag=3.54/.03542 bags
=100 bags.
Is This Answer Correct ? | 2 Yes | 0 No |
Post New Answer View All Answers
how to take the quantity of block work and plastering 1block price:3saudi riyal cement:1bag:15 saudi riyal sand:3bag:20 saudi riyal 1mason:9hour per hour 40 saudi riyal 1labour:9hour per hour 40 saudi riyal can anybdy calculate
1. What is coefficient use for calculation of shuttering. 2. What is coefficient use for calculation of reinforcement in one cum of concrete.
how will calculate 4"thick solid block quantities 1m3 sand cement ratio and breack up detail
Describe about the Pile test methods, which are used in Industrial & Multistory Buildings in general.
Explain the different types of building contracts?
a rectangle grill of length 72 inch x 20 inch width.how to calculate bar spacing ,bar consist 8 mm thickness and spacing of bar is 2 inch.. calculate no of bar with formula
How many square meter can mason layout chb per hour
What is hybrid foundation?
What are your future hopes for this job?
how much of the strength comes from post-production curing
Tell me about triple point of water.
How to plan a project
what is anchorage length,lap length and (dont remember the last one)
how to determine the correctness of proportion used in cement mortor and various IS codes to determine the same?
what will happen if one could not properly follow the spacing of slab reinforcement bar?