Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

How to calculate the cement, sand quantity for plastering?
(10'x10')10mm thick ratio 1:5. wht"s the formula?

Answer Posted / ankit kumar

10 feet= 3.048m
Area=3.048*3.048=9.29m2
Thickness of plaster is 10mm or 0.01m
Volume of plaster = area*thickness
= 9.29*0.01
= 0.0929m3
Add 30% to fill up the joint,uneven surface etc
30% of 0.0929m3 = 0.027m3
The quantity of motar=0.0929+0.0279
=0.1208m3
Increase by 25% the total dry volume
25% of 0.1208m3=0.0302m3

Total dry volume= 0.1208+0.0302
= 0.151m3
For 1:5 sand motar.
quantity of cement=0.151/(1+5)
=0.02517m3
And for quantity of sand 0.02517*5=0.12585m3
Density of cement= 1400kg/m3
One bag of cement =50kg
Then volume of one bag cement=50/1400
0.0357m3
Now bag of cement=0.02512/0.0375
=0.67 bag i.e almost one bag

Is This Answer Correct ?    8 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Analyze the rate for 1st class brick work in superstructure with 1:6 cement sand mortar. Consider 1000 cu.ft quantity and work out the rate per cu.ft

1886


what is project?

2383


How to calculate cement, water, fly ash amount for 1 cum if the w/c ratio is 0.4 and fly ash to cement ratio is 1:9

2073


What is the difference between chamfer and fillet?

1457


What expenses counted in contingencies and how much it is in related to built-up area of the building.

1784


Please let me know about answer for my Question as "What is the maximum wastage allowable of HYSD Steel in any Bridge project as per Code and Code reference also ?

1873


Design a shear wall of length 4.20 m and thickness of 250mm subjected to the following forces.Assume Fck = 25Mpa and Fy = 415Mpa and the wall is a high wall with central part 3440mm x 250mm and two 380mm x 760mm strong bands at each end with following loading. S.No.       Loading        Axial force      Moment     Shear 1               DL+LL          1950              600            20 2           Seismic load       250              4800          700

1991


Why are separation membranes used between concrete pavement slab and sub-base?

1397


2. What are the advantages of your present job, things you like about it?

3126


What should be the standard roof height like to be?

1221


What is meant by solid geometry?

1075


What are the uses of layer?

1340


How much area, in square meters, will one liter of paint cover if it is brushed out to uniform thickness of 600 microns?

6754


How u can calculate the Octagon ring distance from center of raft in 275 mtr chimney slipform errection? cantact no:0993455097

2263


please, what is the required bar for a column of 6mx6m the dept is 405mmx300mm,its an axially loaded ?

1555