We are installing a 1.6 MVA transformer at our crusher plant and the feeder of HPSEBL is 2 km away at substaion .
and a VCB is installed in the substaion which is 2 km away from transformer so we need another VCB near the transformer.
Answer Posted / sarthak
VCB must be installed as you are using quite a good capacity transformer.
Which needs better protection and the VCB at the sub station will not be that helpful ,
if ever you need to do maintainence job on your t/f you task will become easy.
Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
how to calculate short circuit current for the busbar
what is 30-phase of transformer
what is the basic need of domestic loads 1- voltage 2- current
What is resonant peak?
Can we put 3 layers of cable tray while installing tray
what is power factor ? how we can calculate the low power factor and amount of capacitor for improve that low factor ?
Merits & Demarits of Oil circuit & Air circuit breakers ?
testing of Vector Group – YNaoD II
In Air circuit breaker LSIG protection unit is used. Without fault in cables (2 runs 3Cx150Sq.mm Copper, 1Kv grade, XPLE armored cable IR value is more than 550Mohm @ 500V Megger) and load section Long time Overcurrent protection is triggers and trips the unit. We changed LSIG protection with new factory tested unit. Even then fault is persisting. Please suggest the possible causes
What is a DC series motor?
what is magnetizing current test in power transformer
What is the difference between in Fourier series and Fourier Transform. and please tell me the difference between both of them and the why we use them in communication system?
What is your acheivements
how to conduct dc resistance test for rotor of an alternator and how to measure the rotor dc resistance value theoritically?
What is milivolt dop test in Busducts? What is its significance & procedure to do the test?