When alarm is activated in buccholz relay in transformer

Answer Posted / spl

Depending on the model, the relay has multiple methods to detect a failing transformer. On a slow accumulation of gas, due perhaps to slight overload, gas produced by decomposition of insulating oil accumulates in the top of the relay and forces the oil level down. A float switch in the relay is used to initiate an alarm signal. Depending on design, a second float may also serve to detect slow oil leaks.

If an arc forms, gas accumulation is rapid, and oil flows rapidly into the conservator. This flow of oil operates a switch attached to a vane located in the path of the moving oil. This switch normally will operate a circuit breaker to isolate the apparatus before the fault causes additional damage. Buchholz relays have a test port to allow the accumulated gas to be withdrawn for testing. Flammable gas found in the relay indicates some internal fault such as overheating or arcing, whereas air found in the relay may only indicate low oil level or a leak.

Is This Answer Correct ?    3 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is the formuala to calculate the rating of motor protection circuit breaker

1728


In the Variable Voltage Variable Frequency Drive, how the Voltage and Frequency varied ? Is it varied in the Inverter part of the Drive ? Please give us supporting document if any.

1519


how much GROUND & NEUTRAL VOLT maintain in data center.

1540


it is possible to measurement of tension of slipring induction motor(SRIM)carbon brushes, any maesuring instruments are available in the markets.

1500


at work i have a genertor/alternater what is the easyest way to work out if it is dc or ac?

1389






What are the site acceptance tests for power cables, DG Sets, LT panels & 30kVA UPS ?

1904


How is the speed of a DC shunt motor related to the armature current?

681


what is lumped and distributed elements?

1553


What is difference between safe PLC and normal PLC

1000


What is trip and closing coil in cb? Why need of them

1019


what things to be considered when designing UPS

1308


I am completed DEEE in tamilnadu, now i am working in andhrapradesh with 2.5 year experience in relavent field. capacity of the tranformer is 11KV, 1MVA Transformer, i am eligible for getting c licence in andhrapradesh pl help me.

1133


WHAT IS THE DIFFERENCE BETWEEN GENERAL INVERTER AND SOLOR INVERTER TELL ME PLZ

1670


What is the formula to calculate the rating of power cable for three phase current.

1669


What is PEC??Applications........

1510