Vendor has SAP ERP in the system. Buyer sent material to vendor. Vendor processes the material and sends the finished goods to Buyer. What is the process to be followed at Vendors ERP?

Answer Posted / abhigya sharma

subcontracting reverse process

Buyer provides material A to Vendor and Vendor processes Material A and provides Material B to Buyer.

1-Sales order for Material B,
2-MB1C with 501-E Mvt for Material A
3-Production Process for Material B, Issue A in Production. order & get B in Stocks,
4-Delivery
5-Billing

Is This Answer Correct ?    8 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What are the lot size attributes a material can posses?

701


How did different versions of sap evolve?

664


Differentiate between release procedure with and without classification

659


What are the main master files used in mm?

713


What about standard edition (initiate) users?

547






How do we create a vendor number range?

633


If you want to make item ok check boix as default then what will you do?

624


What is the difference between contract and scheduling agreement?

601


What are departmental views?

761


What is the subcontracting cycle?

600


Why is negative stock needed in an organization?

774


Differentiate between contract and scheduling agreement

668


What mrp procedures are available in mm-cbp (consumption based planning)?

674


What is mrp list?

715


What sap program is used to update or create material master records?

685