Answer Posted / lava kumar.v
1. Run first set to voltage and frequency and switch to the main bus bar
2.connect at least 25% Load if regulation is poor.
3.set upto voltage and frequency.
4.synchronize phasing up to bus bar manually or automatically
Above mentioned points are satisfied the Dg will ready for operation
* Adjust engine power as necessary if it takes most of the power it will go out over load ,This will bring down the system.
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
how to find impedance , mutual indatnce in transmission lines
What is the tipical Online UPS input voltage for 20 KVA load ( 3 Phase or 1 Phase )? Why ? Explain it...?
How many types of circuit loads are there in a common electrical circuit?
what is the transformer rush current?
how to control dc motor?
i have flexible wire. size of conductors is 0.190 mm & no.of conductors are 48. then size of wire comes 1.37 sqmm instead of 1.5 sqmm . the what is tolerance for this size.
What is a diode?
what is capacitor voltage transformer?? how it is different from potential transformer?
what is level 2 automation?
What is meant by positive and negative feedback?
how we find transformer capacity by ohm
We have given to 3phase supply to ups system & how can coming netural
in HT service 3ph 4 wire service Y-phase voltage shows zero . whether it is meter fault? or what be the reason ? if y-ph voltage zero ,can current is recorded? reasons for failure?
What should be the height of basement according to NBCC code?
11 kv input, 66 kv input advantages