under which situation or why restricted earth fault protection operates in out side its zone that is external fault
Answer Posted / hg
1) if any one ct saturates at through fault current due to
a) high harmonic content of current in through fault current leading to high voltage appearing across secondary and the ct saturates
2) under above scenario if there is no stabilizing resistor/ damage to stabilixing resitor than relay may operate
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
what is the meaning of SST300 V56A in SIEMENS turbine
What is surging in a centrifugal compressor ? How it occur's ? How is antisurging done ?
operation
what is restricted earth fault explain in details
How do you consider that you can improve and what assistance do you need to achieve this
procedure of how to generate power in solar plant.
How to calculate boiler capacity? I have 1 Autoclave, Which has to use for AAC block. Dimension for this Autoclave is - 13 Meter Length & 2.2 Meter Diameter.
some one can tell me how residual type excitation is provided through transformers to an AC generator without any battery or PMG&excitor
What is LB-SR.
can dp type level transmitter work in under vaccum condition
how to differentiate between "ALL fuel lost" and "All Fuel Lost" in Boiler MFT condition?
explain how the third harmonic content of the magnetising current affects transformer design
DCS marshaling Cabinet Power supply can be replace during plant running time? Answer Yes it is possible. I am talking about the controller and cards power supply modules. They are always redundant and connected through diode so that if one power supply fails the other can take the charge immediately.so it is possible to replace one of them in running plant if the other one is healthy. MY question is how switching done.
what is natural frequency of turbine shaft .
Qatar Fertiliser Company (QAFCO) Shortlisted me for interview (got the intel from my source) for Field Operator- Utilities post. Please let me know what kind of questions they asked? ... this position requires 5 years of experience in Power Plant and background Diploma in Electrical/ Mech. ... my Background is Electrical and I am a sub Assistant Engineer (Operation) at a private HFO based Power plant... PS: Please Let me know what preparation should I take to obtain the Interview which will be take place In Bangladesh soon