how to find number of 16mm bar reqired for 5m length with 125 mm spacing ?
Answer Posted / esantharaj
Number of bars =(l/s)
=(5/.125)+1=41 nos
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
What is the difference between Grade I, II and III of GSB?
In an aggregate blending plant, water is sprayed before blending is performed. If the fine content in aggregate is as high as 25 %, will not the fines form into lumps / balls and distribution will not be uniform ? Further, the fines will stick onto the interior of pug mill and its content will be low. The mixed material is stockpiled for weeks / months before use. Will it not be better that blending is done in dry condition, and water will be added only during compaction at site. Please forward your comments and suggestions.
Please tell me any one, how many quantity concrete paver block fixing perday ( 8hours) per mason??
Explain what is the difference between built area and super built up area?
The 4 main factors to start a construction project are––
please send me bhel questions on rupesh.017@rediffmail.com
In which code the the maximum height of concrete casting has been explained
what is Short bored pile foundation.
please briefly explain calculating or estimating steel quantity for a RCC column?
flow of fluid takes place viscosity compressibilityu surface tension deformation under shear force
What in your past experience or education prepares you for the position for which you are applying
Define current ucs?
How to Calculate Materials Required for PCC 1:4:8 for 1Cum & Brickwork 1:4 for 1Cum & Plastering 1:4 (15mm Thick) for 100Sqm & RCC 1:4:8 & 2mt ( L1=1mt & L2=1mt ) length of 12mm Steel bended in 90degrees what is the formula to calculate Weight & Actual Length ?
How to arrive dry volume of concrete (1.52 to 1.57) ?
How can we calculate 8- storied Madrasha Building pile capacity by taking SPT value at site?