configuration steps of Asset Under Construction (AUC) linked to Internal Order.
Answer Posted / suresh kumar pratapa
IO--->AUC---->Asset
IO------------->Asset
1.Define AUC asset Class(select line item settlement)-OAOA
2.Define asset class for main asset-OAOA
3.Define Order Type-KOT2
4.Create Internal Order(IO)-KO01
5.Create AUC Asese by Using the asset class created in step -1.
5.1.Assign AUC Asset in the IO Settlement rule
6. Procurment against IO & Book expenditure--MIGO/FB50..
7.Settle the IO to AUC-KO88
8.Create main asset(use asset class created in step-2)
8.1-Maintain/ Assign main asset in the AUC asset settlement rule
9.Settlement of AUC asset to Main Asset after completion of Asset
AIAB-Distribute
AIBU-Settle(receiver)
Jounranl Entry
Dr AUC asset
Cr P&L IO Settlement A/C (CO-CEL Category-22)
ATT=115 (Acquisition from settlement from Co to Assets)
After settlement, go and check in Ko03..===you can observe IO balance is Zero..
Go and check AW01N or AS03--values should update..
AS03-General data tab--observe Capitalized on XX/XX/9999
IO with Investment measure--it is a special scenario.. here AUC created automatically..s
| Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
What is a special period?
What are the other modules to which 'financial accounting' is integrated?
How many normal and special periods will be there in fiscal year, why do you use special periods?
What is cost element? : cost center accounting
How do you carry-forward account balances?
What do you mean by net postings? : fi- general ledger
What is an account group? : fi- general ledger master data
How data flows from pp into fi & copa? : co-pa
What is stored in table t001 ?
What are the requirement of using dunning?
What are the features of APP programing
Hi Experts, What is Auto Debit in SAP? please of any body know let me know the answers Regards, Inthiyaz
Explain the process of calculating the planned activity output through long term planning?
Describe mass change/how do you achieve this? : fi- asset accounting
What are the interaction with abaper in project especially for screens, conditions and cutover plan?