on 22.03.2015 at 17:15hrs Y phase 66kV class Power Trf-2 Current transformer has flashed over and oil came out. The failed CT has been replaced on 24.03.2015 at 13:15hrs and the Trf has been charged in presence of RT Hassan after conducting the pre-commissioning tests. On the same day at 17:00hrs the commissioned CT has again flashed over and immediately the Trf has been isolated from power supply. It is confirmed the secondary is not opened and checked the earth integrity and is found ok. Here what would be the reason for the CT failure?
Answer Posted / dheeraj.yadav
It may be cause due to meter internally circuit open the secondary of ct in meter.due to circuit problem.
| Is This Answer Correct ? | 0 Yes | 0 No |
Post New Answer View All Answers
DEAR SIR,I GOT THE CALL LETTER FROM RRB, SECUNDERABD AS A JE-II SO PLEASE PROVIDE ME SOME MODEL QUESTION AND ANSWER PAPERS AND LAST YEAR QUESTION PAPERS
How to calculate VCB rating for 33KV ,25 MW Power line?
what will happen if frequency is below 50 hz?
how can i find cable size from current rating?
why Y CONNECTION IS BETTER INTERMS OF EFFICIENCY AND P.F FOR A LAOD LESS THAN 40% AND WHY AFTER DELTA IS BETTER FOR > 40%
SUTIABLE FOR ohm's law super conductor
Has someone here done a sizing for a generator (3 phase), its for a pumping station. If you have an example for standby/duty and both running (I) star delta (ii) Soft Starter.
Why squirrel cage motor can only use with low starting loads ?
why in a swquence network representation, the negetive sequence generated voltage is taken as zero?
explain the functions of main isolation switches
What are the advantages of autotransformer?
Why we use circular(Stepped) cross section in transformer core?
plz tel me syllabus and exam date 4 jr executive engg (electrical)
What are the no-load losses for the 11000/415V transformer with the following rated capacity? 1.1500 kVA 2. 2000 kVA 3. 2500 kVA 4. 3000 kVA
How servo stabilizer works.