what is relation between planned delivery and GR processing time .
Answer Posted / pratap barik
Planned delivery means Number of calendar days needed to obtain the material and GR Processing time means Number of workdays required after receiving the material for inspection and placement into storage.
Is This Answer Correct ? | 6 Yes | 0 No |
Post New Answer View All Answers
what are the data contained in the information record?
Hi, I have 7+years experience In purchasing a new and doing sap-mm training, how is market for mm and how to find job as sap consultant, Pl help,
How is the mm module integrated with other modules of sap?
Why do we use document types in sap?
What do you mean by reservation?
How is subcontracting used in case of mm?
For creating a purchasing info record what are the pre-requisites?
Suppose you are doing business with one of your own sister concern. You are purchasing certain material and you want to post invoices directly to po (without gr). Which facility in sap mm will you use to map such process.
What is use of material type unbw?
What are the transactions that will result in a change of stock?
What is a mrp area?
Explain how sd and mm are connected in sap?
What is a business area?
How is the inventory management integrated with mm?
Explain the 'purchasing group' concept in mm?