Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

How is rate analysis prepared for M 25 grade of concrete?

Answer Posted / simarpreet upweja

Total Cost will be Material cost + Labour cost + Mode of pouring + mode of mixing and transit + Shuttering Cost + Curing cost in later stage

Material cost will include cost of water + Recron(any fiber if adding) + admixer + coarse aggegate + fine aggregate + sand + Cement + Flyash (if using crush sand).

There are many ways of mixing.
i) If using batching plant then cost of transit millers and plant.
ii) If mixing is done at site by mixer then there will be no cost of transit.
iii) If mixing is done manually then it will be covered under labour cost.

Labour Cost : Self Explanatory

Shuttering Cost : As per surface area multiplied by cost per unit area.

Curing Cost : Self explanatory. Curing can be done by many ways so first you will have to decide method.

Is This Answer Correct ?    3 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Explain what is progress payment?

1214


RR masonry rate analysis

3427


Can someone please be curing period of the following according to IS codes Column beam slab brick masonry raft found. and also tell how many hours/day

2080


What materials were used to build the golden gate bridge?

1366


what is zone a n zone b?why the spacing of ring in zone a less.n zone b high?

2078


Kindly post me previous year interview questions with answer for post of DY. Manager (civil engg.) for GAIL, NTPC, IOC, OIL and ONGC etc.

2399


How to arrive dry volume of concrete (1.52 to 1.57) ?

2406


How much for the BRC lapping in full yield and half yield < and which table to get it ?

2581


cud any one send me tech quest paper(civil engg) at tarizus@yahoo.com

2234


What is meaning of FREE STANDING STAIRCASE ?

3090


What is bylayer?

1198


Which is the direction of negative angle?

1157


Which IS Code/American Code applied for coupler test of steel

2668


What are the phases inspections are done by local authority while construction?

1278


A roof has a U value = 0.65 W/m2 .C. Extra insulation is to be provided. This insulation has a thermal resistance = 1.5 m2"C/W. Calculate the new improved U value.

2321