How is rate analysis prepared for M 25 grade of concrete?
Answer Posted / simarpreet upweja
Total Cost will be Material cost + Labour cost + Mode of pouring + mode of mixing and transit + Shuttering Cost + Curing cost in later stage
Material cost will include cost of water + Recron(any fiber if adding) + admixer + coarse aggegate + fine aggregate + sand + Cement + Flyash (if using crush sand).
There are many ways of mixing.
i) If using batching plant then cost of transit millers and plant.
ii) If mixing is done at site by mixer then there will be no cost of transit.
iii) If mixing is done manually then it will be covered under labour cost.
Labour Cost : Self Explanatory
Shuttering Cost : As per surface area multiplied by cost per unit area.
Curing Cost : Self explanatory. Curing can be done by many ways so first you will have to decide method.
Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
WHAT DLC DESIGN IN CONSTRUCTION
can we use PPC for concrete wall, If yes, what is the concrete (PPC & OPC) grade for Non- load bearing concrete wall, load bearing concrete wall & for cellar retaining wall.
What are the problems one might face while having a Cantilever balcony?
Calculate the maximum allowable speed on a horizontal curve of radius 350m if the maximum allowable values of the lateral coefficient of friction are 0.14 and the rate of superelevation is 0.08.
HDPE pipe standard bends using for TSE irrigation? is it possible to use 30 degree?
how to preaper for interview wat they asked in interview give me idea
For what purpose bedding is used under storm water drains?
How many % we consider for lap for reinforcement for estimates
What you understand by building codes?
What is the use of extend command?
What is alternate bid?
What should be the lap length in raft if height of raft is 0.800mm ...it couldn't b 50D or 40D...we just have to join upper and bottom reinforced...is there any formula for determine it...
if dia of inner circle is 42 m and depth is 1.5 m and width is 1 m ,then whait is the quantity of steel?
In Abutment walls (A1 side) why we are adopting fixed bearing (POT-PTFE)?
how much cement sand n bricks required in im3?and how much in plaster?