How to calculate the individuals quantities of cement,sand,and aggregate
having 1:2:4 ratio for 50 cubic meter area.
Answer Posted / palguna
The proportions of
cement-1 ,sand -2 aggregate-4, the sum of total aggregates is 7
the volume of wet cement concrete is 1.54 to 1.57
then the solution is cement = 1x1.57x1440/7= 322.57 kg
(here 1440 is density of cement
for sand = 2x1.57/7=0.4485 cum
aggregate = 4x1.57/7=0.897 cums
| Is This Answer Correct ? | 8 Yes | 4 No |
Post New Answer View All Answers
for a column of size 400*230mm column reinforcement= 8-20x(cant write the symbol,i hope u guys undersstand,something like (fi) column stirups=8x@(4l) 230c/c 1)what does these mean 2)how to calculate quantity of steel for this column(ceiling height 11 ft)
load combinations how many types for staad design purpose?
I want to know the material required per square foot in rcc roof. i.e. steel: kg/foot, cement/foot etc.
What is the difference between engineering stress and true stress?
When column of building is abutting the boundary line,then suitable footing advised is
What is the biggest dam in america?
What are the Types Of DPC and its Thickness used?
for 200 kg of cement how is the mix proportion in kg for m25 grade of concrete
what is diffrence between catchment area,watershed and basin?
how can can column be corrected when the design is not safe ? is the increasing the clearcover a solution?
in one hour , one 200 excavator , how much quantity (mcube)can load ? soil is not hard not soft
What will be weight of 0.5mm GI sheet per sq.ft?
Define What glue is least sticky?
can i get civil engineering test papers.......?????
Why you are leaving present job?