sir, in a industry present pf is 0.54 pf 25hp power is there
its want improve 0.9 pf. which suitable capacity capacitor is suitable please inform me.
Answer Posted / vishwas g. darne
You can use the the degree of P. F. Correction your load is
25 h.p. i.e. 25*746=18650-18.65kW present p.f.is .54 require p.f. is 0.9 degree of p.f. is 1.075 required kVAR per kW is 1.075 Therefore capacitor rating should be 1.075*18.65=20.04kVAR.
| Is This Answer Correct ? | 2 Yes | 1 No |
Post New Answer View All Answers
what is the difference between ups & inverter
While converting delta into star or star into delta ,the three values of resistances remains unchanged .Find out the value?Let In star R1=x;r2=x;R3=x On converting into delta,R12=x;R23=x;R31=x Find the value of x
how mass curve differs from hydrograph.
what is the minimum clearance between a 11KV 150KVAR capacitor cell and series reactor.can a series reactor can be mounted in the same structure of the capacitor cells structure
How to work definite,over pluxing,revers power,OSR relay
What are chief characteristics of state-space method and its techniques ?
What is error of a measurement?
how oil in the MOCB was reduced compared with OCB? what are the features of the MOCB?
how does WTI work ?
What are the application of filter?
Make a list observation on Transformer?
EHV current carrying parts need to have smooth finish,then how can a 245kv GIS with emery finish can run so long?
What are :- AC Distribution Board (Single & Double Front) DC Distribution Boards Distribution Board LT Breaker Panel.
Assuming that a dedicated neutral earthing transformer is provided for each GT generator, when the two generators are running in parallel, has consideration been given that the earth fault current from one generator stator winding be split between the two neutral earthing transformers? If so, what adverse impact will this have on the operation of the 59N and 27TN devices?
why swityard is necessrry requirement in any bis power distributin systems?