At which place Construction joint should provide in slab
and Beam at the time of casting.
Answer Posted / alp
L/4 for Slabs and Beams
L/3 for Columns
| Is This Answer Correct ? | 0 Yes | 1 No |
Post New Answer View All Answers
Explain what is structural frames or systems?
Why is the statue of liberty made of copper?
What type of tensile strength is handling by crank in beam? Thanks.
For Granite Flooring,For Cement Slurry purpose which one is effective of cost control whether OPC or PPC or White cement?
what is smart building materials?
for 16mm thick cement plastring 1:6 on 100 Sq.m.New brick work,the quantity of cement required is.
if mineral admixture add into concrete then what is the differences between full cement concrete & fly ash added concrete of their SP. Gr.?and for the changes of SP. Gr. what is the changes in concrete
How can calculate the requirement of steel bars of rcc slab for 1100 sq ft?
do you think we shall remove un wanted soil for foundation excavation even if the thickness of the soil strata is more than 8m ?
Why should appointment store person for project ? what is the benefits for company ?
What is Architect-Prepared Contract?
what is your role of in previous company as a construction manager
Which tests are performed on soil to decide the type of foundation to be provided.
How do you convert wind speed into force?
Define unit atmospheric pressure? Difference between gauge pressure, absolute pressure?