if we get water mor from 28 days to the rcc concret is this better or have a damag
Answer Posted / santosh
as we know after 28 days concrete attains 90% of its strength
and concrete takes years to attain 100% of its strength so there is no point curing more.it is wastage of water
| Is This Answer Correct ? | 15 Yes | 0 No |
Post New Answer View All Answers
What will you do if you encounter problems like accidents?
how much concrete solid/hollow block are manufacture per 50 kg cement bag in differnent sizes like 400x200x200mm, 400x200x150mm, 400x200x100mm. And need proper ratio as per sale quantity. pls send my mail mathi7599@gmail.com searching last two years not yet get pls find and enclosed pls. need practical analysis.
What is the meaning of Brick- M 35 grade? Is it a common brick or it's a concrete brick?
what is meaning of inverted beam.is it way to provide double mat in slab one at bottom and another at topif we go for provision of inverted beam. shall we construct structure with out plinth beam for us we have to construct small bus shelter
Why are pull-out tests performed for soil nails?
I am practising engineer. I am searching for tutorial of RCC T Girder design Example in staad pro.Do anybody has this?please help
For fine aggregate which is most suitable River sand or crusher sand & why ?
How to calculate cement, water, fly ash amount for 1 cum if the w/c ratio is 0.4 and fly ash to cement ratio is 1:9
how to diffenentiate the fixed beam and simply supported beam in the execution while reading the drawing and how the reinforcement detail will be differ for the above.
How to convert 20 dia bar to 16 dia bar in beam without reducing the steel weight
what is diversion?
The properties of concrete HA-30 and how does it differ with M 30 (specify the important characteristics like workability,strength,mix design,slump test value)and what is the standard relating to it
LET ME KNOW HOW IS CALCULATE RUBBLE WALL .3'00" IN BOTTOM 1' 6" IN TOP HEIGHT 8' 0" AVERAGE. length 200'00". please give correct answer.
design the irrigation canal(b,B,h )head is 3tms of water is supplied to the 200hectars of area and the base period crop is 150days dance to water travels as 35km.the canal section is trapezoidal and also calculate the slop the canal
Design a cantilever slab to carry a live load of 2000 N/m2. The overhang of the slab is 1.20m. b) A slab over a room is 4.75m x 4.75m. The edges of the slab are simply supported and the corners are not held down. The live load an the slab is 300 Kg/m2. The slab has a bearing of 15cm. On the supporting walls. Design the slab as per Rankine - Grashoff theory. Assume weight of R.C.C. = 2400 Kg/m2.