Answer Posted / ashok kumar sahoo
Definition: Operations are carried out at a work center. In the R/3 System work centers are business objects that can represent the following real work centers, for example:
1. Machines, machine groups
2. Production lines
3. Assembly work centers Employees
4. groups of employees
USE:Together with bills of material and routings, work centers belong to the most important master data in the R/3 production planning and control system. Work centers are used in task list operations and work orders. Task lists are for example routings, maintenance task lists, inspection plans and standard networks. Work orders are created for production, quality assurance, plant maintenance and for the Project System as networks.
Data in work centers is used for
a. Scheduling
Operating times and formulas are entered in the work center, so that the duration of an operation can be calculated.
b. Costing
Formulas are entered in the work center, so that the costs of an operation can be calculated. A work center is also assigned to a cost center.
c.Capacity planning
The available capacity and formulas for calculating capacity requirements are entered in the work center.
d. Simplifying operation maintenance
Regards:
FCS Pvt Ltd
Ashok Kumar Saoo
| Is This Answer Correct ? | 4 Yes | 0 No |
Post New Answer View All Answers
Is it possible to assign two different sales organizations to the same company code?
what are the organizational elements required for the sd transactions
Hi, If I assigned Warehouse number to Plant and go for delivery using LT03,getting error message,not able to save.what may be the reason. what may the reason for account determination error.I have done account determination,then also getting error. Regards Mahendra
How to trace changes in sales order how do you trace the changes made in the sales order in regards to changes to the partner function in the sales orders?
how to define and assign value for mini oder value (amiw) condition type and which field cateloge we suppose to choice in v/03?how amiw and amiz work together?
what is difference between individual and collective requirement
What is the client-specific data?
What is the transaction code for assigning company code to fiscal year variant.
i faced one question. when new configuration we do what is the logic behind there?
To what do you assign distribution channels and divisions?
Explain what is the difference between sap credit memo request and sap credit memo?
At present we have the STATIC credit check, for only one customer we want DYNAMIC credit check from next month. no need to go for configuration ? only should go for master data for that only customer.
Give me examples for Medium Priority & High Priority Tickets from your support project? Give detailed error message/ issue ,your analysis,finally how did you resolve that ticket along with detailed procedure & explanation and t-codes if any? I have an interview in immediate future so plzz help me...Please reply asap... Urgent!!!! Waiting for your response eagerly... Thanks in advance
IF u have worked on EDI IDOC, while sending PO to vendor how u connect to the system. Tellme the entire design and steps of the screen. how it looks.When i told we need to create port, partner profile, outbound idoc process. Interviewer not satisfied.
How do you define tax relevancy of master records?