how many stones require for rr masonery work 1cum.
Answer Posted / santosh singh
For random rubble masonry work
1.25 cu m of stone is required per 1 cu m work
Is This Answer Correct ? | 24 Yes | 2 No |
Post New Answer View All Answers
"how can we find the approximate quantity of materials using in a building or total Expenditure in percentage for rough estimate after known the construction area(sqm)".please if you know something about that please post the answer.
I am a civil engineering student and going to attend interview in this week in an IT company.Will they ask me questions about my area of interest or cs
How did street originate in the plumbing term street ell?
if we know load bearing capacity of the soil and building load falling in each footing, then how to choose the type of foundation??? and if it is shallow foundation then which type of shallow foundation should be choosen i.e either strip or isolated or raft or combined or cantilever footing???????
How much quantity of rod binding work by a rod binder per day
How much the quantity of Dry material of Crush for 1:2:4 Concrete, using pan 3/8'' down....
what is the exact dia of 8swg and 10swg gabion wire
Define What is the origin of name Railway Sleepers?
How to do rate analysis for concrete work including shuttering work?
hoe much fine & sourse agregate required for concrete mix of 1: 1.5:3 by volume in Cu.Ft
WHAT R THE GENERAL TECH QUESTIONS ASKED FOR THE INTERVIEW FOR AN AUTOMOBILE INDUSTRY,SPECIALLY DESIGN DEPT
why is the column design?
What the advantages and disadvantage of using 90mm and 100mm bricks for a wall of a house? Thanks for any input.
What is Rankine Cycle?
I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?