how many 1st class bricks in 1cu feet?
Answer Posted / yaseen jan
volume of brick= .75'x.25'x.375'
volume=.070cu ft
now in 100 cft = 100/0.070
=> 1428.57 nomber of bricks
now 10% mortar /////
deduction of mortorr= 10x1428.85/100 = 142.85
nomber of bricks
so net number of bricks = 1428.57-142.85= 1285.72
now for contengencies = 5%
so => 5x1285.72/100= 64.28
now total nomber of bricks= 64.28+1285.72=1350.006 NOMBER OF
BRICKS
HENCED PROVED.
but The problem is that if we find the quantity of mortar in masonry wall we consider that 30cft mortar use in 100cft masonry wall. and if we find the numbers of bricks we deduct 10% mortar from 100cft. so in this situation we deduct 10% and if we find numbers of bricks its 30%. so some problem created here plz solve the problem.
| Is This Answer Correct ? | 11 Yes | 0 No |
Post New Answer View All Answers
How high should the water tank be to provide a 60 psi at base of this water tower?
What is the use of extend command?
WHAT GOAL DO YOU HAVE IN YOUR CARRIER?
How much cement and water required for cement selery????
how to calculate cut length of re-bar in a circle . because we not place same length of re-bar in whole circle maximum in center and minimum at corner so how to calculate middle bars???
what is tension footing?
Define What is diversion tunnel in a dam?
How to calculate dry of volume of concrete constant?How it comes 1.54 or 1.57
why should we use 20mm graded metal only in vrcc?why we shouldnot use 40mm metal?
what is the types of surveying?which type of survey carrying for type of work?
Define What are the materials used in building a gravity dam?
1.Why we are preferring 43 grade cement than 53 grade cement. 2. Approximate cost difference between 43 and 53 grade cement. Thanks.
What will be weight of 0.5mm GI sheet per sq.ft?
what are the Task work of different labour.?
how to find out hard strata in bored pile when the DMC method adopted.