Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how we are desining 63.5 ohm resistor for NGR of alternator?

Answer Posted / vg

to limit the earth fault current generator/Alternator NGR design. ex. for 11KV generator Earth Fault Current to be limit on 100 Amp.
V=I*R
R=V/I
so I=11000/1.732*100=63.5Ohms.
11KV generator NGR 63.5 amps for 100 Amp fault current.

Is This Answer Correct ?    8 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

acb(AIR CIRCUIT BREAKER)NOT CHARGING AUTO

2301


our factory is going under construction mean time transformer 1000 kva 2 nos &load break swithch 12 kv & 4 nos 750 kva 2 nos & 380 kva 2 nos generator to be errcted.how to arrange earth pits &how to earth connect & neutral pit how to calculate in earth bit size.

2058


What is signal flow graph?

1048


what is apparent poewr, reactive power, & active power?

2241


hwat type of motor is used in thermal gas turbine hydro nuclear power plants and why

1834


how we can decide that what value of ht line will come to any commercial building? (ans except According to the building load)

1594


What are the advantages and disadvantages of the ac motors?

1036


what is meant by surge? what we called for high currents?

1938


What is the difference between alternator and generator?

1247


How eddy current generation support the idea of train braking?

1921


in ring main system we use the isolater b/w transfer bus and main bus if we r not use isolatar than wat will be the effect in our sys.

2026


what is per unit calculation?looking for simple and strong explanation thk u

2505


what is load despatching

2155


Please clarify, 1. Is it required to lay two runs of GI wire along with Armoured LT cable if it is laid between one big mains (63Amps TPN SDF) to small main (32A TPN SDF) with proper glanding termination? 2. If the armoured cable with proper glanding is laid from DB to CNC machine, is it required to run two runs of body earthing to the Machine from DB? 3.If the armoured cable with proper glanding is laid from Substation to Hangar, distance is approx. 100 mtrs, is it required to do earthing at shop area though the primary termination at substation is earthed through gland.

1987


For refrigerators the motor current is raised beyond its rating on both conditions when the voltage of the system is more(say 270v) than the rated voltage(220v) as well as when the voltage of system is less(say 160v) than normal voltageof 220v, why explain?

1922