How much percentage of silt contain maximum allowed?

Answer Posted / azam.tamboli

7% for R.C.C and 4% for Brick / Plaster work.

Is This Answer Correct ?    6 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what is work of planning deptt. in any construction compny (in road project)

1869


A Cat excavator loader of 3Lm*3 heaped capacity bucket is to be used to load blasted rock directly into a crusher of capacity (consumption) of 100L

1544


Can someone please be curing period of the following according to IS codes Column beam slab brick masonry raft found. and also tell how many hours/day

1578


WHAT IS THE % OF CONCRETE WASTAGES PERMITED IN A LARGE PROJECT ? AND WHICH IS CODE TO BE REFERED.

1567


how water proof chemicals act in concrete to avoid leek?

1759






what is the sequence of the activities in the typical under ground water tank including civil & MEP works.

1946


how many time use of plywood shuttering and IS code

2682


how much quantity of 1.5" nails and 2.5" nails are required for conventional formwork shuttering?

1206


I want to know the material required per square foot in rcc roof. i.e. steel: kg/foot, cement/foot etc.

1513


 rcc floor to floor  4m. in column reinforcement where we provide lap in exact location.     

1483


What is the number of IS code of practice to be followed for hydraulic design of sewerage pipe line?

2152


What are wooden shingles?

796


Define What is passive earth pressure ?

685


What is the frequency of sampling for the materials of cement,Fine aggregate, Coarse aggregate .and refer which code

1839


Who built the sears tower?

627