Answer Posted / carl_ellis
24Vdc is the DC power supply voltage.
For 2 wire loop powered instruments, the DC power supply is
in series in the loop.
For 3 wire instruments, the DC power supply common (-)
shares a terminal with the receiver's common (-),
but has a separate (+) terminal.
For 4 wire instruments, there separate wiring terminals for
both the power supply (+) and (-).
Carl Ellis
Measure First
| Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
How to calibrate Magnetic flow Transmitter in Field
when the instrument tapping on pipe line is located below and transmitter is located above the tapping point for liquid service transmitter, what should we do, is there any additional drain valve is required??
HOW TO SOLVE PROBLEM WITH ENRAF LEVEL TRANSMITTER 854 ATG THAT PASSWARD DO NOT Exist INTO TRANSMITTER TO ADJUST LEVEL WITH PORTABLE PET 847, WRITTEN WRONG PASSWORD , I AM SURE THAT DEFAULT PASSWARD (W2=ENRAF2) IS THIS TRANSMITTER NEED TO REPLACE SOFTWARE AND HOW?
Why mixer nd grinder Is example of constant torque load not variable torque load ???
For crude application in floating roof tank, how to calibrate a DP Transmitter? How is the floating roof weight considered?
I have energy meter for educational project having 0.5s class but my friend need 0.2s class meter , which one is good for that purpose and what is the actual difference of that two classes , need very easy example also.??
How to measure the dust in chimney(spm)?
A flange is used for instrument connection for a system with a design temperature of 316C (600F) and a design pressure of 1000 kPa (145 psi). What is the class rating of the flange to be used for this application? Explain your answer
Q- What are the application in which PNP transistor is preferred over NPN ?
A PLC is programmed to drive three motors A, B and C as follows : After running motor A for an hour, motor B should get ON and motor A should get OFF. And after running motor B for an hour, motor C should get ON and motor B should get OFF. And after running motor C for an hour, motor A should get ON and motor C should get OFF. (That is, a cyclic repetition with time period one hour) Now, the second condition is: If any motor gone faulty and is tripped, the consecutive motor should get ON and the faulty (tripped) motor should be eliminated from cyclic repetition. The remaining two motors should bear the cyclic repetition of one hour each. (For healthy motor take logic as high and for tripped motor take logic as low) Now, the third condition is: When motor A load(Amps) exceeds 60% of its rated load, motor B should get ON in parallel to motor A. And when both motors A & B are running in parallel, and if their load exceeds 60% of their rated load, motor C should also start in parallel to A & B. [Here the cyclic repetition is eliminated, until their loads become normal(40%)] [Take logic high(1) for load at 60% and logic low(0) for load at 40%] Now draw a flow chart or a ladder diagram to fulfill the above condition.
how to calibrate steam control valve in steam turbine
what is the procedure of O2 sensor(ABB) calibration?
Area classification, Equipments, Gas groups, temperature classification, Ingress protection, Fire Extinguishers.
Working principle of magnetic flow meter ......and calibration procedure of e+h magnetic flowmeter...
wich is coming the first HAZOP OR SIL