how amny bricks of size 240 mm X 120 mm X70 mm are required in
100 cubic meter brickwork. How much cement is required at 10
mm masonry and at 4:1 sand cement ratio and how much cubic
meter of sand is required for the above work.
Answer Posted / vijayshankar
1 Brick = 0.24*0.12*0.070 = 0.002016 Cu.m
For 1Cu.m = 1/0.002016 = 496 Bricks
For 100 Cu.m = 100*496 = 49600 Bricks.
Cm ratio 1:4
Consider the thumb rule method 25% of Cement mortar
required for the brick work
=0.25*100= 25Cu.m of Cement mortar
That means 25 Cu.m of Sand is required
Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
primary treatment of sewagw consist of removal of floating materials removal of sand & grit removal of organic materials all above
What do we mean by partial moment release ??
I am called for interview from north east power plant .so, I need some interview question which may help me.
why are you joining in this (applied post) job and your aim for this job
How much cement,sand,bricks and water needed for 1square metre brick work?
Explain what are the skills required to become an architect?
what is the most suitable foundation when construct a bird watching tower in a marshy land
Are you ready to relocate with your immediate family to United States as a new employee?
What ingredients with% found in ppc cement??
how statics is different from dynamics
what is smart building materials?
how many shuttering material required for 1000 sq.m built up area.
What is the use of extend command?
What does civil engineering mean?
how we can find sieve #4 is 4.75mm?