Difference between wbm and gsb in road construction
Answer Posted / surajit dey
Wbm full form is water bound macadam and GSB fullform is granular sub-base.
| Is This Answer Correct ? | 151 Yes | 7 No |
Post New Answer View All Answers
2. In a container filled with each of the following materials, at a porosity of 40%, determine the upward gradient required to cause the quick condition (a) Lead shot with a G = 13.75; (b) Fibre beads with G = 2.15; (c) Sand with a G = 2.32
What is the force exerted by the tacoma narrows bridge?
How is calculate the cube molt
Where is the worlds longest elevator and how long is it?
50 acre of land to be reclaimed for an average height of 2.5 mt. Dredging area is 500mx200m size. what is the dredging depth required to reclaim the area?
How to calculate plastering for elevated water storage tank
Which code is used for tor & tmt steel bar?
Design a built-up column carrying an axial load of 1200 KN. Its length is 8m and it is effectively held in position at both ends and restrained against rotation at one end. Assume yield stress of 250 mpa
For submitting the project loan for bank Residential bldg,Suppose we take Provinding RCC mix 1:2:4 for footings No of footings,length ,Breadth,Height ,qty in cum, at last unit/Rate(Rs) ,i would like to know how do we get the unit/Rate
what are the changes in concrete pour height as per IS 456, 2009?
What is the difference between 53 grade and 43 grade cement
What is the crank length in the slab?
how water proof chemicals act in concrete to avoid leek?
How do you compute volume of airflow?
Which condition will prevail for the design of a swimming pool ? When the pool is empty or when it is filled ?