how many safeties should be present in boiler?what are they?
Answer Posted / arun
Totally 9 SV are There
Drum - 3 ( left side-1 , right side-2 )
SH Outlet( MS Line ) - 2
RH Inlet - 1
RH Outlet - 3
This is for BHEL 210MW Boiler
Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
what is the meaning of SST300 V56A in SIEMENS turbine
LAPT working in alternator / generator
Which will have more strain energy 1.Spring 2.Circular disc 3.Solid square plate.
im try to calculating seawater flow required for SW-FGD system. I need a guide, equation or method to do it, can some one help me! Thanks very much
By any way can we increase the B check hours from 300 to 500
our 125 kva DG does not start in AUTO mode works normally in MANUAL mode please give me a solution.....
why is the in steam turbine axial displacement of active side thrust pad is positive and non active side thrust pad is negative.
Looking for Bently Nevada surplus 3300/52-01-00-00 Reverse Rotation Monitor , 4 pieces.
what is natural frequency of turbine shaft .
How to calculate power press toneage
We have Demin Closed cooling water system with expansion tank for cooling oil system. Expansion tank having N2 bladder. Whenever N2 bladder bursts out, Closed cooling water circuit pressure drops and make-up happening, eventhough there is no leaks. And how Circuit pressure drops?
DCS marshaling Cabinet Power supply can be replace during plant running time? Answer Yes it is possible. I am talking about the controller and cards power supply modules. They are always redundant and connected through diode so that if one power supply fails the other can take the charge immediately.so it is possible to replace one of them in running plant if the other one is healthy. MY question is how switching done.
operation
what is the difference between compensated & normal drum level in boiler drum?
Qatar Fertiliser Company (QAFCO) Shortlisted me for interview (got the intel from my source) for Field Operator- Utilities post. Please let me know what kind of questions they asked? ... this position requires 5 years of experience in Power Plant and background Diploma in Electrical/ Mech. ... my Background is Electrical and I am a sub Assistant Engineer (Operation) at a private HFO based Power plant... PS: Please Let me know what preparation should I take to obtain the Interview which will be take place In Bangladesh soon