Answer Posted / nag

Resolution Type:
After receiving defect report from testing team, the
responsible development people are conducting review meeting
and sending resolution type to the responsible testing team.
There are 12 types of resolutions, they are

1. Enhancement: The reported defect is rejected, because
this defect related to future requirements of the customer.

2. Duplicate: The reported defect is rejected, because this
defect raised due to limitations of hardware devices.

3. Hardware Limitations: The reported defect is rejected,
because this defect raised due to limitations of hardware
devices.

4. Software Limitations: The reported defect is rejected,
because this defect is raised due to limitations Software
Technologies (Ms-Access).

5. Not Applicable: The reported defect is rejected because
these defects have improper meaning.

6. Functions as Designed: The reported defect is rejected,
because the coding is correct w.r.p.t design documents.

7. Need More Information: The reported defect is not
accepted / not rejected but the developers are requiring
more information about the defect to understand.

8. Not Re-producible: The reported defect is not accepted &
not rejected, but the developers are requiring correct
procedure to reproduce that defect.

9. No Plan To Fix It: The reported defect is not accepted &
not rejected, but the development people are requiring some
extra time.

10. Open: The reported defect is accepted & the development
people are ready to resolve through changes in coding.

11. Deferred: The reported defect is accepted, but postponed
to future release, due to low severity & low priority.

12. User Direction: The reported defect is accepted, but
developers are providing some valid information about that
defect to customer site people, through our application
build screens.

Defect Tracking Procedure

Large Scale Organizations

1 to 5 --- (Defect reporting)
6 to 10--- (Resolution Type)



Test Manager Project Manager


Test Lead Team Lead


Test Engineer Programmer


Small / Medium Scale Organizations

1 to 4 -------- (Defect Reporting)
5 to 8 -------- (Resolution Type)


P.M


Test Lead Team Lead


Test Engineer Programmer












Bug Life Cycle / Defect Life Cycle

New



Deferred

Open Reject




Closed Re-open


New Open Closed

New Open Reopen Closed

New Reject Closed

New Reject Reopen Closed

New Deferred

Is This Answer Correct ?    1 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is a test severity and test priority? difference between them with suitable examples?

1298


i have source and target having same data structure 500 fields and one lacks records. how to validate data. write 5 scenarios.

4788


What is strategy to be followed for execution of 500 Test Cases in One day. If only 1 Resource is available.

1480


need answer interviewer will ask me about all project which i mention in resume or presently i'm working??please reply tomorrow is my interview

1612


What is the difference between load testing and performace testing?

680






How many types of api testing are there?

644


what is a horizontal and vertical matrix explain with examples

2106


What are the Major Functionality for a ATM machine ??

4969


What are the cases why parameterization is necessary when load testing the Web server and the database server?

1582


can anyone help me regarding testing patterns?

1559


Define what is a critical bug.

659


what are the advantages of manual and automation testing ? and which one would u term as efficent testing and effective testing ?pls do reply thankx in advance

1432


Can you explain process areas in cmmi?

618


What is un-installation testing?

649


What is an end-to-end testing?

611