11kv alternator commissioning test?

Answer Posted / naveen singh

Before commissioning of alternator following electrical tests should be done on site-
(1) IR and PI of generator
(2) Winding resistance of generator
(3) IR and winding resistance for PMG and excitor field winding.

Is This Answer Correct ?    19 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what is the condition for YnD11

2661


why and how voltage sharing in transformer, during magnetic balance test ?

2450


What will happened if the neutral of the (star connected secondry) Xformer disconnected? (if its Above KVA rated one)

2258


please send me previous year questions of jspl through which i could prepare myself for the test.

1970


XYZ

2239


what is thermal resistance of PVC Cable.

1903


why lightning arrestor are made in two stack of insulator but why not cvt

2157


What is the basic principal, by which DC voltage level is increased more than the supplied AC voltage during conversion. As upto AC level it is contorrled by firing anlge but after maximum level how is it possible.Please clear picture. OR we have to supply the higher level AC?

2055


DRAW ACIRCUIT DIAGRAM OF 100 KVA 415V/55-0-55V DELTA TO STAR TRANSFORMER

2135


CBCT selection

2363


xfhnchncv?

1983


Sir, I have applied for the of Assistant.engineer of NPDCL. please send me all AP TRANSCO AND JENCO solved papers of previous exams . I requested send me the papers to my id as soon as possible (rajanikanth_peddi@yahoo.co.in) (This is very urgent) Thank You,

2990


how to avoid electrical shock how capacitor store charges wat are the speed control of induction motors state faradays law flemings left hand rule what is rotary converter wat is transmission and distribution what are the sources of energy abrevation of acb,vcb,sf6,igbt what is output equation of transformer which test copper iron and iron loss are calculated what is eddy current draw a single line diagram (10 marks) draw direct online starter(10 marks)

2072


i karmveer bharti persuing b.tech . plz send me syllabus and name of reference books. for preparation of section eng.

2215


If not into production, how far did you follow the design and why did not you see it into production?

2261