Answer Posted / naveen singh
Before commissioning of alternator following electrical tests should be done on site-
(1) IR and PI of generator
(2) Winding resistance of generator
(3) IR and winding resistance for PMG and excitor field winding.
| Is This Answer Correct ? | 19 Yes | 1 No |
Post New Answer View All Answers
in basic 2 phase will short means tripping the power but spot welding 2 phase shorting but not tripping it will welded why.....(Q)
How one can check the MAIN of a house wiring ?
what are all types of cross section in AC cables?
while doing high potential for 11KV 3 core cable how much leakage current will obtain?, what will be acceptance value?
Why back emf used for a dc motor? Highlight its significance.
When we connect the large capacitor bank in series ?
Why can't we parallel the secondary circuits of two voltage transformers?
what is meant by power and distribution transformer ?
please give me solution to rectify the emi(electromagnetic interference)
1.how many earth pits are required for 1000 k.w plant include substion , transformer ? 2. how many earth pits are required for 500kva generator.what is formula to calcute?
at work i have a genertor/alternater what is the easyest way to work out if it is dc or ac?
A 100W electric lamp is supplied from a 115V, 60HZ source. The peak instantaneous power dissipated in the lamp filament is
what is meant by neutral compensation factor and where it is used
I want formula to calculate current loss with distance in km.I searched many sites but didn't right answer.Plz reply me
What is the importance of counter based plan & how is it scheduled?