How to find quantity of cement mortar?
I want to know the req quantity of cement for plastering 300
sft in final coat with 12 mm. Any math involved? Plz help
Answer Posted / sachin
Assume proportion 1:5
total work = 300 sq.ft.
convert in m3 = 27.87 m3
thickness is 12 mm = 27.87 *.012
total volume = .33 m3
proportion is 1:5 = 1+5 = 6
so = .33 / 6
so = .055
cement per bag volume is 1440/50 = .034
so .55 /.034 = 16.17 bag
| Is This Answer Correct ? | 0 Yes | 2 No |
Post New Answer View All Answers
How does a traffic light signal work ?
1. HOW MUCH CEMENT AND SAND REQUIRED TO PLASTER 100 SQM WALL. 2. HOW MUCH CEMENT AND SAND REQUIRED FOR SCREED WORK OF AREA 30 SQM
2nd and 4rt angle elevation used in which country ?
all technical question
Minimum concrete cover in slabs, columns, beams, foundation and other st?
How much time Required for PPR pipe network testing
What are the steps involved in the concreting process?
How much material will consume for following specification water tank (9*7.5*6 feet)?
Material calculation of cm 1:6 for 1sqm
I want to know the material required per Square foot in rcc roof i.e.Steel ,Cement,
How much quantity of cement,sand,stone used to build 1 cum of cc road??
Define the various stages of the project planning process in construction.
How many lbs are there in a yard?
In csae of hume pipes NP stands for Non Pressure bur what does it really mean?
I have a slab of 20cm thickness of 20m by 4m in wich we are installing 15 tons electric panels , and we have put 4 H-shaped columns under the slab but we have done many cores in the slab which seems very normal , can you help me by telling me how to calculate the bearing capacity of the slab or give me an idea if i should increase more columns Note: load distribution area 12*1.5 m2