how many average of shuttering in one cubic meter concrete
Answer Posted / ilias mahammad
Shuttering Qty can be taken as approx.5-6 times the volume
of concreting.
i.e. for 1 cum of concreting approx. 5.00sqm-6.00sqm
shuttering is required.
| Is This Answer Correct ? | 19 Yes | 3 No |
Post New Answer View All Answers
what will be the cost of thickness of 125mmor rcc measurement of 52x33.75 feet
what values & beliefs have guided you in your career path
For elevated service Reservoirs what will be the output of each skilled carpenter and bar bender.
How does siphoning work?
Actually i am confused that how to calculate the bending moment for a semi-circular beam and curved slab.If any one have a good idea about the matter,please give the answer with a suitable example. Thank you......
For what building Built-on balconies are preferable? What are the advantages?
usually hand broken stones are used for cement concrete 1:4:8 in foundation of single /two story houses with a view of economy in construction.what advantages it will give if you use machine crushed stone in place?
in staad pro. modelling for a parallel scissors chord truss, when i assigned roller support i.e fixwd but with all Fx, FZ, Mx, My and Mz release except Fy... the analysis results " in stability at a joint, with direction Mx or My..what could be the reason...anyone please explaing
How did street originate in the plumbing term street ell?
How you read 5x3x1 #4 @ 20" 0/C in steel structure?
How to find out kg per Sft ?
how to calculate weight of 1.8 cum of aggregate
Dear sir, i want to NBCC & NTPC previous exam papers email Id : madhu_bingi@yahoo.co.in
Explain what is change order request?
Slump Values for works?