What are the prerequsites for costing transactions?

Answer Posted / jagannath

For Costing Labour Time in Oracle Project Costing you will need to make sure that following setup is done.
1.
You have defined Labour Cost Rate Schedule for the Organization / Operating Unit ( cost rate schedule can be defined at various level of the organization Hierarchy )

2.
You have defined cost rates for each of the Job that is assigned to Employee Assignment. ( I am assuming you are defining cost rate for Job).
It is important that you have got Job associated with employees on the cost rate schedule.
3.
For the Cost rate defined above, you have associated Organization and Cost Rate schedule in Organization Labour Costing Rule.

4.
If you are doing burdening, you need to define burden schedule and all associated setup for Burden schedule ( like, burden cost code, Burden cost base, burden structure ...etc ) and burden schedule should be compiled

Is This Answer Correct ?    0 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Is there any possibility for having custom schema at any time when it is required?

456


How can I setup a child org to be its own costing organization?

519


Explain Rule based optimization in oracle apps?

494


Define sql loader ?

508


What is multi org architecture?

512






What responsibility do I need to use to setup organization?

545


How to enable tracing for document managers

460


Which are the kinds of report triggers?

611


Define descriptive flexfield ?

556


What is oracle apps (erp)?

521


What is the usage of the spawned object?

529


How to attain parameter value depending on the first parameter?

474


What is flexfield?

501


Which are the attachments that are platform independent and become a part of the template?

808


Define mrc ( multiple reporting currency)?

543