Number of cement bags required for concreting 1000 square
Feet slab of 4 inch thickness.
Answer Posted / ashwini
If the grade of concrete is M25 and 330 KG cement per cubic
meter of concrete. Then the answer is 61.31 bags of cement
is required.
Is This Answer Correct ? | 39 Yes | 26 No |
Post New Answer View All Answers
how we can find sieve #4 is 4.75mm?
five requirements of infill panels for walls?
sir I got selected in rail vikas nigam limited and they call for interview but i don't what they will ask in interview please guide me if you have any experience
Define What is rigging?
what is right & short method of measurement of slab&beam
Pile height is 4.3m. 2nos. under reammer. bulb nose is 75mm and height is 400mm. pile dia is 375mm and overall dia 940mm.pls. help to calculate concrete in pile and bulbs separately. What is formula for bulb volume calculation ?
how to calculate total cost for slab 35'×8'
how much st. steel is required for staging of concourse slab of a elevated metro station allowing through traffic .
As we know that steel is a tension member but why we are using STRUCTURE STEEL as a COLUMN (Without concrete) where column is a compression member and compression strength of steel is very low
What is alternate bid?
how to compute slab reinforcements on step by step procedures??
i am completed my b.tech EEE in 2009,,,iam trying the job 3+ for AUTO CAD (ELECTRICAL),, what is the market for autocad electrical in hyderabad... how to handle the intervws give some suggestions ?
how to tie 10 legged stirrups
what is moment-curvature relationship in semi rigid connections??
Discuss some applications of modular elasticity?