I am working in a process industry, in that there are
several sections devided in the SCADA screens and
individual sections may START independently. But sometimes
i am facing problem i.e, if section 2 Stopped by the
operator immediately Section 1 or Section 3 or Section 4 is
getting stopped can you expain the reason behind this?
Answer Posted / sks
this might be due to 2 reasons :
1)scan cycle of the processor has been increased anyhow as
the Dword value is updated after the signal is processed in
module. this extended scan cycle causes difference of
process values on HMI
2) check LAN ports of all stations and also the patch board,
if there is option for redundancy check the healthiness of
redundancy.
| Is This Answer Correct ? | 0 Yes | 1 No |
Post New Answer View All Answers
I am manjunath having exp in maintenance of chemical plants,know i want to do a design course INTOOLS,after doing design course can we get jobs in design field.sinve i dont have design exp..
-/5A. What is the meaning and limitations of this in energy meter constant. It is a 3 phase LT Energy Meter. If this Energy Meter is connected through a CT of ratio 200/5 Amps, then what is the multiplying constant and how its will be calculated.
what is the importance of CV in the control valves? how it is calculated?
Why mmwc unit is used?
can u briefly explain aboutan aryton shunt multirange DC ammeter?
How is work 5/2 sov?
How to control flow variations in magnetic flow maters..... When i will provide proper earthing?
How to measure the dust in chimney(spm)?
please send me some question papers of HPCL aptitude test ?? please send it to bipinb.28@gmail.com ...
What is the advantage of using locally fabricated hook ups over Pre fabricated hook ups in process instrumentation?
What is the GK Value in Flowmeter?
Isometric drawings are generated during _________________ phase of a project
Full form of KKS when use DCS.
What is rang ability?
how to relay switch sense the fault?