Onsite percentage wastage of Concrete, Rebar, Blockwork/Brickwork, Plaster, Floor tiles ??
Answer Posted / karthik rajendren
3% for Concrete & rebar
5% for Brick/Block Work,Plaster& Tile
| Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
How to decide/consider the grade of bitumen for dbm.
what is the meaning of degreasing of the euipment or line.
What is binding spacing of the rebars at lapping zones.
Why reinforcement done in shorter span in two way slabs
i have a interlock pavement work.i need to compact about 2000 sq metres of sub base grade c of thickness 15 cm.what is the amount of water required for compaction ??
what is the soil bearing capacity for a 5 floor multistorey residential building and which type of soil ? what is plinth beam? in wall load calculation center to center column distance is considered or not/
What is meant by Crystal Concrete?
How to calculate brick work quantity?? Block work quantity??
how to calclate the SHUTTERING TAKEN CONCRETE LOAD? WHAT IS THE LOAD BEARING CAPACITY IN STEEL SHUTTERING PLATE? WHAT IS THE CONCRETE LOAD IN (MASS) IN THE SHUTTERING PLATE. PLATE SIZE IS 120CM* 90CM CONCRETE WALL LENGTH IS 10M ,WIDE IS 60CM, HEIGHT IS 1.2M PLS TO SENT THE CALCULATION.
what is the formula for Mass of cement grout (Dg)=???
What is the amount of work done by a carpenter, bar Bender and plaster Mason in interior and exterior plaster
How much area, in square meters, will one liter of paint cover if it is brushed out to uniform thickness of 600 microns?
What is meant by dimensioning?
How to calculate the quantity of ingredients of M20 grade concrete?
Discuss some applications of modular elasticity?