how to calculate rate analysis for column shuttering
Answer Posted / rustam jamal
Assume Column Size- 1.200x0.300 and Height = 3.000
than Qty for Conc. = =1.2x0.30x3.0= 1.080Cum
Shuttering Area = 2x1.2x3.0=7.20
= 2x0.30x3.0=1.8
Total =9.0Sqm
In 9.0sqm Shutterin 1.08 Cum Conc. req.
so For 1 Cum Shuttering Qty = 8.333
In case of Columns we required 8.33 sqm of shuttering area
in 1 Cum of Concrete
| Is This Answer Correct ? | 88 Yes | 31 No |
Post New Answer View All Answers
importance of the soundness test to determine the quality of cement use for any construction
How much permissible bearing capacity requires for open footings(isolated) and what type pile foundatuon prefering for coastal areas?
how much of the strength comes from post-production curing
What are the uses of groynes?
I just got a first job in Maharashtra and m a fresher. My task is estimate the cost of excavation of earth with J.C.B. can anyone tell me how to do this??
can stub column take the load as main column
what is the permanent solution applied for restoration of leaning tower of pisa?
Please send me the qunty. of mason/labour required in each day for different type of civil construction work?please send me ans. in my mail.my mail id is (parthamitra086@gmail.com) or here.
How to Calculate Materials Required for PCC 1:4:8 for 1Cum & Brickwork 1:4 for 1Cum & Plastering 1:4 (15mm Thick) for 100Sqm & RCC 1:4:8 & 2mt ( L1=1mt & L2=1mt ) length of 12mm Steel bended in 90degrees what is the formula to calculate Weight & Actual Length ?
how to estimate costing from quantity givin in BOQ and according to this how we fill tender and final rate for perticular work.....?
detailed calculation of the amount of cement used?
Why is the statue of liberty made of copper?
i am completed my b.tech EEE in 2009,,,iam trying the job 3+ for AUTO CAD (ELECTRICAL),, what is the market for autocad electrical in hyderabad... how to handle the intervws give some suggestions ?
how to calculate quantity of cement,sand & aggregate for u.c.r / r.r masonry in cm 1:6
is concealed wiring a problem in fly ash brick wall?