how to calculate 1:2:4 ratio concrete cement, sand, metal
and water please give me brief calculation
Answer Posted / venkatesh babu rj
Cement - 1 Part
Sand - 2 part
Aggregate - 4part
Cement = 1440 x 0.9/4
= 324Kg/m3 or 6.48Bags(324/50).
Sand = 1440 x 0.45/2
= 324kg/m3.
Aggregate = (1.25x4x6.48)/35.315
= 0.917Cu.m
| Is This Answer Correct ? | 4 Yes | 3 No |
Post New Answer View All Answers
How to determine thee cut length for steel reinforcement bars in R.C.C design
What do you understand by “preset” during the installation process of bridge bearings?
How about the temperature of grade 35A concrete? Does it depend on the ambient temperature?
What is change order request?
Floor to floor high of domestic building is 3m design a quarter turn staircase starting assume taken give a suitable diagram of it?
On what basis we decide the formation level of the road? other then that of 50% Cutting and 50% Filling??
how to calculate spacing rod in column
why should we use 20mm graded metal only in vrcc?why we shouldnot use 40mm metal?
psc girder detail
I need model question papers for writing the Dubai municipality exam,for G+1
how to read the drawings to find the quantity of steel in a storm water manhole or any other structure?
How to calculate thickness of MAT slab & Reinforcement? The dimention of under ground water reservoir is 80'X14'X 12 ft
Difference between lime, distemper and plastic emulsion?
what isload waring calculation
How to calculate Acctually Brickwork Quantity in Honey Comb Brick in circular Soak Pit