how do we calculate quantity of cement , sand and
aggregates in 1 m3 of M30 grade concrete ?
Answer Posted / rahul mehta (g.m. projects)
M30 design..Cement:1/4*1.54=.385*28.8=11bags per cuM,Sand:.385*1=.385cuM,because dry density 1.54=wet density 1.54 in concrete work
Is This Answer Correct ? | 7 Yes | 1 No |
Post New Answer View All Answers
residential buildings,mixing of concrete,structural,construction material,site handling.
how to disign cuplock shuttering and it's matireal requirement snd any related web site
Design a reinforced concrete combined footing (rectangular) for two columns located 3.60 metres apart. The overall sizes of the columns are 40cm x 40cm and 69cm x 60cm and the loads on them are 1000 kn and 1500 kn respectively. The space available for the width of the footing is restricted to 180cm. The S.B.C. of the soil is 280 kn/mm2 use M15 concrete.
what are the challenges of being a team leader and a supervisor?
what is detail procedure of eccentric footing? plz. give solved exmple?
which are the Indian auther books for STONE COLUMN/GRANULAR PILES?
Which is the indian standard code of line out. ? How much tolerance fot 1 mt lenght? Its challenge....
what is the use if we fixed butterfly ties in column and masonry work joint?....where we have to fix(distance)..
questions with answers to face an interview of an civil engineer regarding RCC buidings
What black man invented the clothes dryer?
Does brick grows bigger every year?
Why are steel plates inserted inside bearings in elastomeric bearings?
how to read the drawings to find the quantity of steel in a storm water manhole or any other structure?
Please let me know about answer for my Question as "What is the maximum wastage allowable of HYSD Steel in any Bridge project as per Code and Code reference also ?
Describe about the Pile test methods, which are used in Industrial & Multistory Buildings in general.