Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

what is mean by loop checking?

Answer Posted / shreeyash nandurkar

Loop Checking
Some think of loop checking as
a process to confirm that the
components of the loop are wired correctly and is typically
something
done prior to start-up. However,
due to factors described in the
introduction above, the loop check’s
scope has expanded to also include
tests to confirm that it is “operating as designed” and then
to ongoing
programs for benchmarking and monitoring performance. The block
diagram in Figure 1-5 illustrates the
components of this expanded loop
checking process.
This process starts when the instruments are received at the
plant site.
It continues through installation and
start-up and into the ongoing plant
operation. In addition, the control system should perform
the intended
function properly. This includes
verifying the transmitter’s process
variable (PV) for display to the operator, for use in the
control strategy,
and for historical trending. This verification testing prior
to start-up is
known as the factory acceptance test
(FAT) which, as an option, can be
duplicated at site with the actual hardware and software
installed, termed
site acceptance test (SAT). Further discussed in Chapter 2,
the FAT can be
performed prior to shipment of the
hardware or in parallel with the
hardware installation
at site if the overall start-up schedule is compressed.
Once the technician checks the control strategy to verify
that the
expected output to the final control element is produced,
the loop can then
be commissioned and start-up can proceed.
Finally, the loop check can include defining the loop
performance
benchmark and providing a method for monitoring the
performance over
time.

Is This Answer Correct ?    11 Yes 3 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

what is sliding spool valves?

2293


Why trim span ? How?

1678


principle of dead weight tester ?

2128


I want to know the questions asked in ONGC interview(after being selected in the written exam) for Instrumentation branch.Kindly help.

2341


Basically iam Instruemntation Engineer, but Iam interested in Instruments design engineering, so plz guide, is there any course, training or Softwres to become Instrument design engineer??.

2094


What you mean by multi stage control vavles?

1848


Why use ball valves on Gas pipelines instead of gate & or globe valves...means basic diffrence or use of these valves..how designers knows this type of valve with rating is required...

2394


What are different types of control valves?

1662


how to turbine speed measurement?

1627


plz you help about Que paper of mahagenco previous your,any model paper relad to it{maharastra power genration}

2369


sir i m preparing for BARC but i am not getting any papers to prepare for this exam so please send me some sample papers to my i.d for the preparation of barc.

2501


What is standard of DCS panel design?and what is step of DCS panel design?wiring and type of connector(screw or DB connector)

2156


What are de-saturators?

1293


hi i am eswar i want to know the instrumentation interview questations for eil(engineers india ltd) i have applied for engineer post in eil please help in this.my mail id eswar310@gmail.com

2613


What is limitation of the ht.of the displacer of a level trol?

2459