yokogawa Temperature transmitter showing Error 15 which is Reverse Cal Fail (confirmation calculation result is bad) in manual they mentioned reasion That the output goes to the value set by hardware failure mode jumper. How can solve this problem ? anybody can say solution
Answer Posted / carl_ellis
In the manual (from which you cited) the user action for
error 15 is 'contact service personnel'.
You can try that, but I suspect that it means, for all
practical purposes, replace the transmitter. I don't know
if Yoko offers a spare 'puck' that can be replaced in order
to salvage the housing and display, or not. You'll have
to ask.
You might try cycling power to it to see if an electrical
spike on the loop wiring adversely affected the processor,
and cycling the power might re-initialize it, but the
likelihood of success is very small.
When a transmitter goes to fail-safe mode, it's usually the
last act of the last performance, the actors are clasping
hands, and taking a final bow before the show closes.
tell 'em Carl sent you
| Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
Why does a pressure gauge installed on reactor, doesn't have any vent line below to release the pressure? Is it any kind of designing mistake or it actually does not require any vent line? And if it does not require any vent line below it then how we are gonna release the pressure built inside the pressure gauge?
How many are the types of instrument cables in terms of No. of pair.
With N nodes and B branches what will have a network ???
If a control valve is hunting means means if we are giving 50% to the cv, the cv will open at 51% then slowly slwoly it will reaches 49% , so what to do for solve this problem. The cv is double acting and mounted for anti surge operation, it having 4 nos. volume booster, one sov, one positioner, etc..?
In power plant to measure vibration of a turbine we install sensors. Before install this sensor we have to set gap voltage. What is meant by gap voltage and its use?
key phaser where is use and work
where i can get training in INTOOLS and PDMS in Delhi-NCR OR north part of India. please reply with ur ans. at arunsamkaria@ymail.com
please tell me what is a light up procedure of Cfbc boiler and what it's axuillaries of cfbc boiler?
Regarding , there is an air cooler which control the fans(50% of AV FANS) by temperature in outlet , and the louver of Air cooler is controlled by HIC from control system , So if on Air cooler we will consider 2 individual I/P converter or positioner?
Can anybody please let me know Orifice plate sizing calculation formula and step by step procedure
anybody having Qatar Petroleum questions for instrument Technician offshore ....please send me
what would be the minimum flow rate that we can measure on rotameter..?
what is the input to be given in digital flow meter during the the calibration time?
What is three element in drum level?
i am from instrument branch i want paper patern of mahagenco . any pevious years paper regarding my branch send me please . please.....