HOW MANY CUBES REQUIRED FOR 7 AND 28 DAYS TEST FOR ALL MIX
GRADES.

Answer Posted / rajah

As per IS 7 days is not required but 7 days result is just a cross checking (7 days result must more than 77%)

for 28 days
concrete in cmt no of samples(3 cubes)
1) 1 to 5 1
2) 6 to 15 2
3) 16 to 30 3
4) 31 to 50 4
5) 51 and above 4 plus one additional sample for
each additional 50 cmt

Is This Answer Correct ?    23 Yes 9 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is costing in 100squre feet bricks

1405


please, what is the required bar for a column of 6mx6m the dept is 405mmx300mm,its an axially loaded ?

1143


How to build the floor to ceiling bookcase?

818


For what purpose bedding is used under storm water drains, explain?

736


at which depth the construction of tunnel is economical from cost and engineering aspect.

1304






sir when can we expect the AEE results and when will be the interviews sheduled please guide us in this regard thanking you

1994


What is the snap size in civil and how can we create it?

2304


Define unit atmospheric pressure? Difference between gauge pressure, absolute pressure?

1675


what is cross hair cursor?

641


Difference between lime, distemper and plastic emulsion?

1228


quantity of material needed for rubble stone masonry for 1:4 and 1:6

1215


How much of fly ash is allowable in Portland cement and what is the disadvantage when the level of fly ash is increased?

1365


for G+2 residential building how much quantity of required in foundations,sub & superstructures per sq ft area

1892


how statics is different from dynamics

1234


what is the formula to find the sttel (bar)length in beam having bent up at l/4 t 45 degree & 60 degree.

2136