HOW MANY CUBES REQUIRED FOR 7 AND 28 DAYS TEST FOR ALL MIX
GRADES.
Answer Posted / rajah
As per IS 7 days is not required but 7 days result is just a cross checking (7 days result must more than 77%)
for 28 days
concrete in cmt no of samples(3 cubes)
1) 1 to 5 1
2) 6 to 15 2
3) 16 to 30 3
4) 31 to 50 4
5) 51 and above 4 plus one additional sample for
each additional 50 cmt
| Is This Answer Correct ? | 23 Yes | 9 No |
Post New Answer View All Answers
Design a built-up column carrying an axial load of 1200 KN. Its length is 8m and it is effectively held in position at both ends and restrained against rotation at one end. Assume yield stress of 250 mpa
Why you are leaving present job?
Describe a time when you anticipated potential problems and developed Preventive measures
Can a wave happen in the middle of the ocean like in the movie poseidon 2006?
What are the advantages of cad software?
How can we convert weight batch to volume batch for m30 mix
i have span of 6m x 4m how do i calculate the reinforcement of steel i needed and to at what distance and also the thickness of slab. looking forward thank you RAVI
What is the meaning of a blue land surveyors flag?
Explain major differences between routing maintenance and major maintenance.
What is demising walls?
how many tonnes equals to one cubic feet?
what will be the total emoluments for deputy surveyor in APPSC in the payband of ( 9460-27600). please give me the detailed information step wise?
Why was the empire state building made of steel?
Define What is the tensile strength of wood?
How to calculate the force on a column of three story building. What should be the base concrete height?.