What is refurbishment order ? Explain the total cycle ?
Answer Posted / keerthi kittu
Refurbishment order is one of the maintenance order
type.Generally it is PM05.This order used when there are any
damaged equipments in the plant.Then the person who is
responsible for that plant,uninstall the equipment from plant.
Then the equipment is moved to material warehouse of
particular section(where damaged equipments are present).
After they got particular count of damaged materials
refurbishment order PM05 is created.Based on the order we
know the cost associated to these damaged materials.based on
the order refurbishment activities will performed like they
will send(to vendor) those damaged materials to
refurbishment purpose.After refurbishment, equipments state
is changes from damage to refurbishment.Once the problem is
over the refurbished equipment is reinstalled in plant.
| Is This Answer Correct ? | 0 Yes | 2 No |
Post New Answer View All Answers
Which all modules you can integrate with sap pm?
How a general task list is different from equipment and functional location?
What is difference between single cycle plant and maintenance strategy plan?
How is corrective maintenance different from breakdown maintenance?
Can I maintain two different units in a measuring point?
What are activities of a sap pm?
How would you attach a drawing to the equipment master data?
What are the key responsibilities in sap plant maintenance?
What is purpose of serial numbers in sap pm module?
What do the ik08 tcodes in sap- pm mean?
Can we change equipment category once defined?
What do the me21n tcodes in sap- pm mean?
How do you define an own view for alternative label?
Which table would you use to extract the equipment hierarchy installed under functional location?
You tried to install an equipment on a functional location but system gives you an error. What could be the possible reason?