if the synchronizing b/w
generator and busbar not
complete and we close the
out going circuit breaker
of generator then what
happen ?
Answer Posted / sheikh
if synchronization b/w generator and busbar would not be
completed and if you close the out going CB then generator
have gone to over current tripped or reverse power tripped
Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
Dear all i am kumaravel. now in chennai. my work is control and relay panel auto cad designing.up to 11kv to 400kv then question is i am improving my knowledge. i want some books name and auther are available for this C&R panel related. plese any one help me
1- What is the Polarization Index number be good for 15KV 3c#500MCM electrical cable? 2- Can I use the IEEE Std 43-2000 to perfom the PI test? Thanks
if we have a industrial load of 400 kilowatts with 415 volt AC then how much total harmonic distortion (thd%) should be acceptable for steady power system.
Which type of motor is used in trains, what is the rating of supply used explain working principal?
How can I calculate the Mega watts required to run a plant having many electric motors and other electrical components.
why Induction Generators are not "Black start" ? and apart from WTGs where this types of generator are generally used?
Difference between RCCB, RCBO and ELMCB.
explain the process of commutation in a dc machine. Explain what are inter-poles and why they are required in a dc machine.
how to compute kvar in substation feeder to improve power factor and sending voltage
what happens in the short circuited secondary transformer,if the resistance of the short circuit is increased gradually?
what is the difference between general inverter and solor inverter clerly explain plz
How many types of colling system it trformers?
Why is tan-delta test and capacitor measurement done on alternator?
How to Calculate the Fault Level of Electrical Installation
What is difference between Harmonic and Non harmonic Capacitor Bank?