How to replace dia of bar in beam like 25mm 3no.S at bottom
But due to some reason on site 25mm bar is not available
Then is it ok to provide 20mm 4no.S? Give description or
Formula to calculate area of steel and replacement?
Answer Posted / manoj kumar
The formula or the thumb rule for finding of no of bars with spacing .
Let the d= dia of the bar which is to be provided at the place of given bar.
D= dia of given bar in the drawings.
Spacing = d2/D2x(given spacing of bar in dwg.)
for Eg.
d=20, D=25 spacing=200
s=(400/625)x200=128
Is This Answer Correct ? | 12 Yes | 10 No |
Post New Answer View All Answers
i have span of 6m x 4m how do i calculate the reinforcement of steel i needed and to at what distance and also the thickness of slab. looking forward thank you RAVI
How to use of me trial wall plaster 6mm , 10mm par sqm. use in sand and cement ?
Define What is an ice dam sock?
What is the quantity of cement in mix m20 concrete?
what could be the production cost of 1 cum of concrete by CP30 plant
How much Tolerance factors like 1. brick work 2.plaster 3.painting 4.floor tiling 5.wall tiling 6.shuttering 7.concreting 8.steel
Is there the dry coefficient of cement is constant?
how to take the quantity of block work and plastering 1block price:3saudi riyal cement:1bag:15 saudi riyal sand:3bag:20 saudi riyal 1mason:9hour per hour 40 saudi riyal 1labour:9hour per hour 40 saudi riyal can anybdy calculate
How good are the Weinerberger Porotherm bricks that are being used in construction in Chennai, India. Its being used in non load bearing walls and has a compressive strength greater that 35 kg/cm^2 and a density of approx.694 - 783 kg/m3.
What are the methods of measurement? Describe it shortly
Which tests are performed on soil to decide the type of foundation to be provided.
Whats the meanig of ,'K' VALUE in the case of soil.....
what is the theoritical percentage of concrete cubes testing per day?
can you please tell me what the current rate of construction material and different construction labourers charge in bangalore ???
Can anyone suggest how to determine scheduling of reinforcement of floor beams from Staad model,other than clicking each beam respectively 7 noting down the values ?